Sept. 2012 - ED5-to-Thornton Road Line Construction Contract Awarded; and ED5 Substation Instrument Transformer materials contract awarded.
Aug. 2012 - ED5 and Test Track substations contract for 230kV breakers awarded
July 2012 - ED5 Substation contract for a 230/115kV transformer awarded
Nov. 2011 - First draw of Treasury funds for project
Sept. 2011 - Western Administrator certifies project
Sept. 2011 - DOE concurs on project
Sept. 2011 - OBM apportionment approved
Aug. 2011 - A FONSI (finding of no significant impact) certified
July 2011 - Final Environmental Assessment published
May 2011 - Draft Environmental Assessment published
Mar. 2011 - Public Open House held for Environmental Assessment
Feb. 2011 - ED4 signs 50-year Transmission Service Agreement for 156 megawatts on new line west to east
Dec. 2010 - Environmental Assessment process begins
July 2010 - Statement of Interest for long-term purchase of proposed line's capacity
May 2010 - ED5-PVH proposal received from SPPR Group